Price checkDrilled Shafts & CaissonsPer LF

Rock socket, by diameter

What bidders priced on like-for-like public pay items, from public agency bid tabulations restated to 2026 dollars and a typical job, against ESC’s published rate as a general contractor carries it.

Diameter: ESC’s rate against the median public bid

36 in. diameter

−28%

ESC’s rate as a GC carries it, against the median public bid

36 in. diameter: ESC’s rate as a GC carries it is $3,905/LF −28% vs the median public bid, and below 65% of 139 public bids on 23 lettings (2019–2026).

  • Strong evidence: 23 lettings
  • Bids 2019 onward
  • New England agencies
  • Restated to 2026 dollars
  • Middle half of bids
  • Median bid
  • Typical low bid
  • ESC rate, as a GC carries it (gold rule: our low–high range)
ESC published rate
$3,550/LF
Range $1,750–5,350
As a GC carries it
$3,905/LF
Published rate +10% · $1,925–5,885
Median public bid
$5,436/LF
Recent lettings count more; each letting once
Middle half of bids
$3,016–10,729/LF
25th to 75th percentile
Typical low bid
$2,970/LF
Median of each pay line’s lowest bid
Pay lines where ESC is under even the lowest bid
6 of 27
ESC’s carried rate below every bid on the line

Price book note: 36 in socket by rock auger or core barrel. Low: weathered/fractured rock. High: hard granite or gneiss.

This rate in the price book

01 · The field

Every public bid

Each dot is one bidder’s price on one public pay line for this work: 139 bids on 23 lettings, 2019–2026. Every price is restated to 2026 dollars, 36 in. diameter and a typical job size, so it compares like for like with ESC’s published rate. Point at or focus a dot for its year, agency and rank; the other bids on its pay line are ringed.

  • Public bid
  • Older lettings fainter
  • Middle half of bids
  • Median bid
  • Typical low bid
  • ESC as a GC carries it (gold rule: low–high)

n = 139 bids · 23 lettings · 27 pay linesSource: public agency bid tabulations

Show all 139 bids

02 · Size and time

Price by diameter, and over time

Every bid at the diameter printed on its pay line, then the selected size’s bids by the year they were opened.

Price by diameter

Each dot is one bid at the diameter printed on its pay line, restated to 2026 dollars and a typical job. The ink line and band are the median and middle half of every bid restated to each published size; the gold diamonds are ESC’s rate as a GC carries it. Diameter in inches.
  • Bid at its printed diameter
  • Median bid at each size
  • Middle half
  • ESC as a GC carries it

n = 139 bids at 7 printed diametersSource: public agency bid tabulations

Show the numbers

Over time

Each dot is one bid, placed by the year its letting opened. Every price is restated to 2026 dollars, 36 in. diameter and a typical job, so a price bid years ago and one bid last season compare like for like. Ink ticks: each year’s weighted median, where the year has at least 3 bids.
  • Public bid
  • Year’s weighted median
  • ESC as a GC carries it

n = 139 bids · 8 years with bidsSource: public agency bid tabulations

Show the numbers

03 · Pay lines

Pay line by pay line

Every public pay line behind this rate. No bidder, project, contract or town is shown: a line is a year, an agency, a printed quantity, a count of bidders and prices.

ESC’s carried rate would have been the lowest price on 6 of 27 pay lines.

Every public pay line for 36 in. diameter, newest first: year, agency, printed quantity, bidders, and the lowest, median and highest bid restated to 2026 dollars, 36 in. diameter, with where ESC’s rate as a GC carries it would have ranked.
YearAgencyQuantityBiddersLowMedianHighBids on the line against ESCESC would have ranked
2026CTDOT20 LF2$2,317$2,641$2,965#3of 3
2025CTDOT25 LF3$3,044$3,056$3,943#3of 4
2025MassDOT1,780 LF6$465$1,992$5,466#5of 7
2025MassDOT132 LF2$11,394$11,657$11,920#1of 3: the lowest price on the line
2025MassDOT32 LF2$10,688$10,692$10,697#1of 3: the lowest price on the line
2025MassDOT22 LF8$9,356$12,182$15,114#1of 9: the lowest price on the line
2024MassDOT72 LF5$3,517$10,159$12,308#2of 6
2024MassDOT6 LF6$2,688$4,890$9,430#2of 7
2024MassDOT6 LF6$2,673$5,413$9,857#2of 7
2024MassDOT2 LF4$2,892$3,760$4,801#3of 5
2023MassDOT1,585 LF5$4,789$6,386$6,665#1of 6: the lowest price on the line
2023MassDOT80 LF3$1,858$5,437$6,343#2of 4

Newest first · 12 of 27 pay lines

Low, median and high are restated to 2026 dollars, 36 in. diameter and a typical job; the quantity is as printed. The strip shows each bid on the line (dots), its median (ink tick) and ESC’s rate as a GC carries it (diamond), on one scale for every line. “ESC would have ranked” counts ESC as one more bidder on the line.

04 · Agencies

By agency

The same comparison inside each agency’s own lettings.

36 in. diameter by agency: lettings, bids, median bid, the field of bids against ESC’s rate as a GC carries it, ESC against the median and the weighted share of bids above ESC.
AgencyLettingsBidsMedian bid /LFField and ESCESC vs medianBids above ESC
All agencies23139$5,436−28%65%
Massachusetts Department of TransportationMassDOT20125$6,427−39%75%
Connecticut Department of TransportationCTDOT314$3,012+30%22%
  • Middle half of bids
  • Median bid
  • ESC rate, as a GC carries it (gold rule: our low–high range)

Where these numbers come from

Basis

36 in. diameter. 139 public bids on 23 lettings and 27 pay lines, from MassDOT and CTDOT (2019–2026). Every bid is restated to 2026 dollars and to a typical ESC job of 15.5 LF at 36 in. diameter. A letting’s weight halves every 3 years, and each letting counts once, however many bidders it drew.

ESC’s rate is compared as a general contractor carries it: the published typical rate plus 10%, because a public pay line is the general contractor’s price, markup included.

Published by Earth Support Corp. from public agency bid tabulations. These are budget comparisons, not a quote or an offer: ESC quotes its earth-support scope to general contractors as a subcontractor, from your drawings.

Send drawings. Get a firm, line-item quote within 3 business days.

Rev 1 · valid through Dec 13, 2026

Get a firm quote in 3 business days

Or email plans and your bid date to bids@earthsupportcorp.com.