Price checkDrilled Shafts & CaissonsPer LB
Reinforcing cage, furnish & set (or set only)
What bidders priced on like-for-like public pay items, from public agency bid tabulations restated to 2026 dollars and a typical job, against ESC’s published rate as a general contractor carries it.
- 1 published rate
- Price book rev 1 · valid through Dec 13, 2026
- How the comparison works
Furnish, fabricate and set
+25%
ESC’s rate as a GC carries it, against the median public bid
Furnish, fabricate and set: ESC’s rate as a GC carries it is $3.36/LB — +25% vs the median public bid, and below 14% of 26 public bids on 6 lettings (2013–2024).
- Limited evidence: 6 lettings
- Bids all years
- New England agencies
- Restated to 2026 dollars
- Middle half of bids
- Median bid
- Typical low bid
- ESC rate, as a GC carries it (gold rule: our low–high range)
- ESC published rate
- $3.05/LB
- Range $3.05–3.25
- As a GC carries it
- $3.36/LB
- Published rate +10% · $3.36–3.58
- Median public bid
- $2.68/LB
- Recent lettings count more; each letting once
- Middle half of bids
- $2.19–2.89/LB
- 25th to 75th percentile
- Typical low bid
- $2.17/LB
- Median of each pay line’s lowest bid
- Pay lines where ESC is under even the lowest bid
- 0 of 7
- ESC’s carried rate below every bid on the line
Price book note: Shop-fabricated cage delivered with spacers, set in the shaft. Per LB of cage steel.
This rate in the price book01 · The field
Every public bid
Each dot is one bidder’s price on one public pay line for this work: 26 bids on 6 lettings, 2013–2024. Every price is restated to 2026 dollars and a typical job size, so it compares like for like with ESC’s published rate. Point at or focus a dot for its year, agency and rank; the other bids on its pay line are ringed.
- Public bid
- Older lettings fainter
- Middle half of bids
- Median bid
- Typical low bid
- ESC as a GC carries it (gold rule: low–high)
n = 26 bids · 6 lettings · 7 pay linesSource: public agency bid tabulations
Show all 26 bidsHide the numbers
02 · Time
Over time
- Public bid
- Year’s weighted median
- ESC as a GC carries it
Each dot is one bid, placed by the year its letting opened. Every price is restated to 2026 dollars and a typical job, so a price bid years ago and one bid last season compare like for like. Ink ticks: each year’s weighted median, where the year has at least 3 bids.
n = 26 bids · 6 years with bidsSource: public agency bid tabulations
Show the numbersHide the numbers
03 · Pay lines
Pay line by pay line
Every public pay line behind this rate. No bidder, project, contract or town is shown: a line is a year, an agency, a printed quantity, a count of bidders and prices.
ESC’s carried rate would have been the lowest price on 0 of 7 pay lines.
| Year | Agency | Quantity | Bidders | Low | Median | High | Bids on the line against ESC | ESC would have ranked |
|---|---|---|---|---|---|---|---|---|
| 2024 | NHDOT | 4,300 LB | 2 | $2.09 | $2.39 | $2.69 | #3of 3 | |
| 2023 | NHDOT | 425,000 LB | 2 | $2.87 | $3.94 | $5.02 | #2of 3 | |
| 2021 | NHDOT | 71,359 LB | 4 | $2.41 | $2.51 | $2.81 | #5of 5 | |
| 2021 | NHDOT | 47,694 LB | 4 | $2.37 | $2.46 | $2.77 | #5of 5 | |
| 2018 | NHDOT | 51,316 LB | 4 | $2 | $2.60 | $3.10 | #5of 5 | |
| 2016 | NHDOT | 6,500 LB | 3 | $1.99 | $2.19 | $2.19 | #4of 4 | |
| 2013 | NHDOT | 68,495 LB | 7 | $2.18 | $2.77 | $3.28 | #8of 8 |
Newest first · 7 of 7 pay lines
Low, median and high are restated to 2026 dollars and a typical job; the quantity is as printed. The strip shows each bid on the line (dots), its median (ink tick) and ESC’s rate as a GC carries it (diamond), on one scale for every line. “ESC would have ranked” counts ESC as one more bidder on the line.
04 · Agencies
By agency
The same comparison inside each agency’s own lettings.
| Agency | Lettings | Bids | Median bid /LB | Field and ESC | ESC vs median | Bids above ESC |
|---|---|---|---|---|---|---|
| All agencies | 6 | 26 | $2.68 | +25% | 14% | |
| New Hampshire Department of TransportationNHDOT | 6 | 26 | $2.68 | +25% | 14% |
- Middle half of bids
- Median bid
- ESC rate, as a GC carries it (gold rule: our low–high range)
Where these numbers come from
Basis
Furnish, fabricate and set. 26 public bids on 6 lettings and 7 pay lines, from NHDOT (2013–2024; every year is used, because bids from 2019 on leave fewer than 8 lettings). Every bid is restated to 2026 dollars and to a typical ESC job of 9,438 LB. A letting’s weight halves every 3 years, and each letting counts once, however many bidders it drew.
ESC’s rate is compared as a general contractor carries it: the published typical rate plus 10%, because a public pay line is the general contractor’s price, markup included.
Limited evidence: 6 lettings. A comparison is published from 3 lettings; 8 or more count as strong evidence.
Published by Earth Support Corp. from public agency bid tabulations. These are budget comparisons, not a quote or an offer: ESC quotes its earth-support scope to general contractors as a subcontractor, from your drawings.
Send drawings. Get a firm, line-item quote within 3 business days.
Rev 1 · valid through Dec 13, 2026
Or email plans and your bid date to bids@earthsupportcorp.com.