Earth Support Corp

Soldier pile & lagging · Tiebacks · Street permissions

Holding a garage excavation along a city street, with tiebacks under the public way

A developer's six-storey building sits on a one-level parking podium that runs right to the sidewalk, and the cut is about sixteen feet. Along the street, a tieback wall keeps the excavation open and free of bracing. But every tieback crosses the property line under a public street full of utilities, and that needs the City's permission before anyone drills.

Illustrative example — composite site, not a completed ESC project.

Building
Six storeys over a one-level garage
Lot
100 ft × 120 ft
Cut
About 16 ft below the sidewalk
Street side
Garage wall just inside the front lot line
Neighbor
Two-storey commercial building 5 ft past the side line
Ground
Fill over sand and gravel over glacial till; water below the cut (typical; confirm by borings)

The situation

The garage runs to the front of the lot. Its wall sits just inside the property line, with the sidewalk, a parking lane and the usual water, gas, sewer and electric lines under the street beyond.

On the left, a two-storey commercial building on shallow footings stands five feet past the side line. To the right and at the rear the lot stays open, with room to lay the cut back.

At sixteen feet, a cantilever wall would need heavy piles and would move more than a street full of utilities should. A braced excavation would fill the garage with struts. Tiebacks keep the hole open, if they are allowed to go under the street.

What drives the design

  • Permission to go under the street

    Tiebacks that leave the lot need the City's approval (in Boston that goes through the Public Improvement Commission) as well as street-opening and occupancy permits. That process sets the schedule, so it starts early.

  • The utilities

    Every tieback has to pass each pipe and duct bank under the street with room to spare. Utility records and test pits fix their positions before the anchor layout is drawn.

  • The neighbor's side

    No anchor goes under the neighbor's building without a written agreement. That side is braced from inside the hole with rakers instead.

  • What happens afterwards

    Once the building holds the wall, the City may require the tiebacks to be de-tensioned or cut free so nothing is left loaded under the street.

Soldier pile and lagging on the street and neighbor sides, one row of tiebacks under the street, rakers on the neighbor's side, and slopes where the lot is open.

  • Drilled HP12 soldier piles about seven feet apart along the street and the neighbor's side, set from existing grade before the dig starts.
  • Timber lagging in lifts as the excavator comes down.
  • Street side: one row of tiebacks about six feet below the sidewalk, drilled at a downward angle to pass beneath the utilities and bonded in the sand and gravel beyond the soil wedge that pushes on the wall. Each one tested and locked off.
  • Neighbor's side: a waler and rakers braced to footing blocks in the excavation, set out to clear the garage structure.
  • Right side and rear: laid back where the open ground allows.

Illustrative example — composite site, not a completed ESC project.

Section: Podium garage beside the streetIllustrative section on the street side: one row of tiebacks drilled down beneath the utilities, installed only once the City has agreed they may cross the property line.GARAGE EXCAVATION
  1. Note 1: Property line: the street side of it is public way
  2. Note 2: Utilities under the street, located and cleared before any drilling
  3. Note 3: Tieback: free length through the wedge that loads the wall, bond length beyond it
  4. Note 4: Waler and anchor head, tested and locked off
  5. Note 5: HP12 soldier pile in a drilled hole, with timber lagging
  6. Note 6: Garage subgrade about 16 ft below the sidewalk
Illustrative section on the street side: one row of tiebacks drilled down beneath the utilities, installed only once the City has agreed they may cross the property line. Typical values, for budgeting — not for construction. The engineer of record designs.

Illustrative example — composite site, not a completed ESC project.

Site plan: Podium garage beside the streetSynthetic plan: a tiebacked wall along the street, a raker-braced wall beside the neighbor and slopes on the open sides. Not a real lot.Site plan: Podium garage beside the streetSynthetic plan: a tiebacked wall along the street, a raker-braced wall beside the neighbor and slopes on the open sides. Not a real lot.
  • Lot line
  • Neighboring building
  • New building footprint
  • Soldier pile & lagging (piles drilled, not driven)
  • Tieback under the public way (if permitted)
  • Raker brace inside the excavation
  • Cut laid back — no support
  • Gap that decides the design (measured on the drawing)
  1. Synthetic lot for illustration: 100 × 120 ft, with the garage against the street and the left side.
  2. Street wall about 97 LF, full height for about 73 LF and tapering where it meets the right-side slope. Left wall full height for about 93 LF, braced by rakers, then tapering into the rear slope.
  3. Tiebacks drawn one per pile, reaching about 37.5 ft past the property line under the sidewalk and street (plan length of a 40 ft tieback at 20°).
  4. No anchors under the neighbor. The slopes use the lot's own open ground on the right and at the rear.
Synthetic plan: a tiebacked wall along the street, a raker-braced wall beside the neighbor and slopes on the open sides. Not a real lot. Typical values, for budgeting — not for construction. The engineer of record designs.

The order of work

  1. 01Months ahead. Tieback layout, utility test pits and the City application. The permission, not the drilling, sets the start date.
  2. 02Weeks 1–2. Drill and set the soldier piles from grade on the street and neighbor sides.
  3. 03Weeks 3–5. Lag in lifts; stop at the tieback level to drill, grout, test and lock off the row; carry on down, with rakers on the neighbor's side as the dig reaches them.
  4. 04Then. The wall stays for the garage walls, and the tiebacks are released if the permit requires it.

Who carries what

ESC

the earth-support subcontractor

  • Soldier piles, drilled and set
  • Lagging as the excavator digs
  • Tiebacks: drill, grout, test, lock off
  • Waler and rakers on the neighbor's side

General contractor

or the builder

  • Street-opening and occupancy permits, traffic control
  • Utility test pits and locates
  • Garage walls cast against the lagging

Excavator

often the GC's own crew

  • Excavation in lifts, to the tieback level and below
  • Slopes on the open sides
  • Spoils off site

Engineer of record

designs and signs

  • Wall, tieback and raker design
  • Test loads and lock-off values
  • Movement limits for the street and the neighbor

Others

  • City: approval for tiebacks under the street
  • Utility owners: clearances
  • Monitoring consultant: survey points on the street and the neighbor

Budget range

Budget range · budget, not a quote

$420,000$740,000

Computed from ESC’s published unit prices, book rev 1 issued September 14, 2026 and valid through December 13, 2026: the low quantities at the book’s low rates to the high quantities at its high rates, rounded out to the nearest $5,000. It is a budget for this composite site, not a quote for yours.

The basis, line by line

  • Drill rig for the soldier piles, one visit

    $23,750–49,250

    1 LS × $23,750–49,250

    One continuous visit for the pile drilling.

    Book row MOB-DRILL-LOCAL

  • Soldier piles on the street side (HP12 class, 24 in holes)

    $91,000–166,050

    350–410 LF × $260–405 per LF

    About 15 piles: 11 at full height (26 to 30 ft) and 4 shorter where the wall tapers.

    Book row SPL-PILE-24

  • Soldier piles on the neighbor's side (HP14 class, 30 in holes)

    $154,050–261,000

    474–522 LF × $325–500 per LF

    About 14 full-height piles at 30 to 33 ft, plus 3 shorter ones where the wall tapers.

    Book row SPL-PILE-30

  • Timber lagging, left in place

    $92,625–170,800

    2,850–3,050 SF × $32.50–56 per SF

    About 73 LF of street face and 93 LF beside the neighbor at 16 ft, plus the tapering ends where each wall meets a slope.

    Book row SPL-LAGGING-LIP

  • Waler on the neighbor's side, one level

    $21,600–31,960

    90–94 LF × $240–340 per LF

    The length of the raker-braced wall.

    Book row SP-WALE

  • Rakers, budgeted at the book's strut rate

    $37,200–59,150

    6–7 EA × $6,200–8,450 per EA

    One raker at every other pile, about 14 ft apart, along the full-height wall.

    Book row SP-STRUT

  • Tiebacks under the street, with testing and any later release

    Priced per job

    The current book prices anchors to about 20 ft; these run about 40 ft. Priced per job once the City's conditions and the utility positions are known.

Not in this range

  • Excavation in lifts, slopes and spoils (excavator)
  • Utility test pits, street-opening and occupancy permits, traffic control (builder)
  • The City application for the tiebacks (owner's team)
  • Wall, tieback and raker design (engineer of record, or the design-build option if the contract delegates it)
  • Monitoring of the street, the utilities and the neighbor (owner's consultant)

Where a real job lands

The wall is priced from the book; the tiebacks are not. The City's conditions (how many, how deep, and whether they must be released later) set their price.

Low end: open site, repetitive work, good ground, larger quantities. High end: tight access, obstructions, variable ground, small quantities. Book rates carry prevailing wage.

Every rate in the published book

What we’d need to firm it up

  • Garage plans with the wall line and subgrade levels
  • Borings along the street side
  • Utility records and test-pit results under the street
  • The City's conditions for tiebacks in the public way
  • The neighbor's footing depth, and any agreement on access

More on the techniques

Send us the address and drawings

We'll send back how we'd approach yours: the support we'd use, the order of work, and a budget range from our published prices. We work for builders, GCs and developers.

Or email plans to bids@earthsupportcorp.com

CallEmailStart Quote