Describe an excavation-support scheme in plain English and get an interactive 3D model, quantities, a construction sequence, and a budgetary estimate in seconds.

⌘↵ to run

Loading 3D scheme…

Soldier pile + lagging scheme, 18 foot cut, 92 linear feet of wall, Rakers + deadmen, with underpinning. Budgetary estimate $435,715.

Soldier pile + lagging
CUT 18 FT · WALL 92 LF
13 PILES
2-FINGER ORBIT · PINCH ZOOM
Budgetary estimate
$435,715
range $370,358$501,072

Concept-level budgetary visualization. Not a bid; not stamped engineering. Final scope, quantities and price require a site review and a project geotechnical report.

Adjust
System
Soldier pile + lagging
Configuration
76 LF + 16 LF return
Cut depth
18 ft (toe 8 ft)
Support
Rakers + deadmen
Section
W12×65
Underpinning
76 LF (19 bays)
Soil model
boston
CallStart Quote