Price checkSoldier Pile & LaggingPer SF
Timber lagging, install (and remove where required)
What bidders priced on like-for-like public pay items, from public agency bid tabulations restated to 2026 dollars and a typical job, against ESC’s published rate as a general contractor carries it.
- 2 published rates
- Price book rev 1 · valid through Dec 13, 2026
- How the comparison works
Published rate: ESC’s rate against the median public bid
Left in place
−40%
ESC’s rate as a GC carries it, against the median public bid
Left in place: ESC’s rate as a GC carries it is $45.65/SF — −40% vs the median public bid, and below 60% of 35 public bids on 5 lettings (2015–2026).
- Limited evidence: 5 lettings
- Bids all years
- New England agencies
- Restated to 2026 dollars
- Middle half of bids
- Median bid
- Typical low bid
- ESC rate, as a GC carries it (gold rule: our low–high range)
- ESC published rate
- $41.50/SF
- Range $32.50–56
- As a GC carries it
- $45.65/SF
- Published rate +10% · $35.75–61.60
- Median public bid
- $75.58/SF
- Recent lettings count more; each letting once
- Middle half of bids
- $17.83–93.71/SF
- 25th to 75th percentile
- Typical low bid
- $12.52/SF
- Median of each pay line’s lowest bid
- Pay lines where ESC is under even the lowest bid
- 2 of 6
- ESC’s carried rate below every bid on the line
Price book note: 3 in rough hardwood, installed in lifts as the GC excavates.
This rate in the price book01 · The field
Every public bid
Each dot is one bidder’s price on one public pay line for this work: 35 bids on 5 lettings, 2015–2026. Every price is restated to 2026 dollars and a typical job size, so it compares like for like with ESC’s published rate. Point at or focus a dot for its year, agency and rank; the other bids on its pay line are ringed.
- Public bid
- Older lettings fainter
- Middle half of bids
- Median bid
- Typical low bid
- ESC as a GC carries it (gold rule: low–high)
n = 35 bids · 5 lettings · 6 pay linesSource: public agency bid tabulations
Show all 35 bidsHide the numbers
02 · Time
Over time
- Public bid
- Year’s weighted median
- ESC as a GC carries it
Each dot is one bid, placed by the year its letting opened. Every price is restated to 2026 dollars and a typical job, so a price bid years ago and one bid last season compare like for like. Ink ticks: each year’s weighted median, where the year has at least 3 bids.
n = 35 bids · 5 years with bidsSource: public agency bid tabulations
Show the numbersHide the numbers
03 · Pay lines
Pay line by pay line
Every public pay line behind this rate. No bidder, project, contract or town is shown: a line is a year, an agency, a printed quantity, a count of bidders and prices.
ESC’s carried rate would have been the lowest price on 2 of 6 pay lines.
| Year | Agency | Quantity | Bidders | Low | Median | High | Bids on the line against ESC | ESC would have ranked |
|---|---|---|---|---|---|---|---|---|
| 2026 | VTrans | 425 SF | 2 | $12.08 | $43.96 | $75.84 | #2of 3 | |
| 2025 | MassDOT | 8,300 SF | 6 | $30.70 | $102 | $153 | #3of 7 | |
| 2025 | MassDOT | 1,740 SF | 6 | $12.59 | $56.64 | $126 | #4of 7 | |
| 2019 | RIDOT | 2,300 SF | 7 | $28.16 | $93.86 | $282 | #3of 8 | |
| 2017 | CTDOT | 1,702 SF | 7 | $243 | $432 | $778 | #1of 8: the lowest price on the line | |
| 2015 | CTDOT | 35,664 SF | 7 | $51.01 | $115 | $173 | #1of 8: the lowest price on the line |
Newest first · 6 of 6 pay lines
Low, median and high are restated to 2026 dollars and a typical job; the quantity is as printed. The strip shows each bid on the line (dots), its median (ink tick) and ESC’s rate as a GC carries it (diamond), on one scale for every line. “ESC would have ranked” counts ESC as one more bidder on the line.
04 · Agencies
By agency
The same comparison inside each agency’s own lettings.
| Agency | Lettings | Bids | Median bid /SF | Field and ESC | ESC vs median | Bids above ESC |
|---|---|---|---|---|---|---|
| All agencies | 5 | 35 | $75.58 | −40% | 60% | |
| Connecticut Department of TransportationCTDOT | 2 | 14 | Too few lettings to compare | |||
| Massachusetts Department of TransportationMassDOT | 1 | 12 | Too few lettings to compare | |||
| Rhode Island Department of TransportationRIDOT | 1 | 7 | Too few lettings to compare | |||
| Vermont Agency of TransportationVTrans | 1 | 2 | Too few lettings to compare | |||
- Middle half of bids
- Median bid
- ESC rate, as a GC carries it (gold rule: our low–high range)
An agency is compared on its own from 3 lettings. Every agency’s bids count in the charts and pay lines above.
Where these numbers come from
Basis
Left in place. 35 public bids on 5 lettings and 6 pay lines, from CTDOT, MassDOT, RIDOT and VTrans (2015–2026; every year is used, because bids from 2019 on leave fewer than 8 lettings). Every bid is restated to 2026 dollars and to a typical ESC job of 853 SF. A letting’s weight halves every 3 years, and each letting counts once, however many bidders it drew.
ESC’s rate is compared as a general contractor carries it: the published typical rate plus 10%, because a public pay line is the general contractor’s price, markup included.
Limited evidence: 5 lettings. A comparison is published from 3 lettings; 8 or more count as strong evidence.
Published by Earth Support Corp. from public agency bid tabulations. These are budget comparisons, not a quote or an offer: ESC quotes its earth-support scope to general contractors as a subcontractor, from your drawings.
Send drawings. Get a firm, line-item quote within 3 business days.
Rev 1 · valid through Dec 13, 2026
Or email plans and your bid date to bids@earthsupportcorp.com.