Earth Support Corp
On site now

Earth Support · Cambridge

Property-Line Soldier Pile Walls, 194–196 Lakeview Ave

A new building at 194–196 Lakeview Ave is dug out to its property lines on four sides. Every wall has a neighbor behind it, the design carries a 250 psf surcharge, and groundwater sits 6–10 ft down in silt and sand.

1234567
Schematic — illustrative, not for construction; pending PE review.

The problem

A new building at 194–196 Lakeview Ave is dug out to its property lines on four sides. Every wall has a neighbor behind it, the design carries a 250 psf surcharge, and groundwater sits 6–10 ft down in silt and sand.

The engineered approach

Twenty-four HP12x53 soldier piles go into 18 in drilled holes backfilled with flowable fill, about 7 ft exposed over 12 ft of embedment, at 8 to 10 ft spacing along roughly 194 lf of wall. Timber lagging follows the excavation down. The walls are cantilevered to the project's PE-stamped support-of-excavation design, and the rest of the dig is sloped back.

Where it stands

  • Underway now: four property-line walls, 24 soldier piles
  • Built to the project's PE-stamped SOE design
  • Cantilevered walls, with no tiebacks or bracing in the dig

How we're building it

A schematic section of the earth support system for this Cambridge job. Scroll to build it in construction order, or select a callout to read the detail.

Schematic typical section of the cantilever soldier pile walls on the property lines at 194–196 Lakeview Ave, Cambridge: an HP12x53 pile in an 18 in drilled hole backfilled with flowable fill, about 7 ft exposed over 12 ft of embedment, timber lagging between the flanges, a 250 psf surcharge behind the wall, and groundwater 6–10 ft down held below the cut by dewatering by others.An illustrative typical section, drawn as the design intent, through one of four cantilever soldier pile walls Earth Support is installing on the property lines at 194–196 Lakeview Avenue in Cambridge; the work is underway. The wall line is the property line. On the right is the neighbor's side, where the project's PE-stamped support-of-excavation design, prepared by others, carries a 250 pound per square foot surcharge on a ground surface whose grade varies, shown as a strip of downward arrows. On the left is the excavation, by others. In construction order: an 18 inch hole is drilled at the wall line; a steel HP12x53 H-pile is set in it; the hole is backfilled with flowable fill around the pile; the excavation is dug and dewatered by others; and Earth Support places 3 inch timber lagging between the pile flanges as the dig goes down. Each pile stands about 7 feet exposed above the bottom of the excavation over 12 feet of embedment below it, about 19 feet in all. There are no tiebacks and no bracing: the walls are cantilevers. Twenty-four piles at 8 foot and 10 foot spacing make up about 194 linear feet of wall over the four walls. An enlarged plan inset at top left shows two piles, each in its 18 inch hole of flowable fill, with lagging boards spanning between them behind the excavation-side flanges, and the 8 or 10 foot spacing broken in the middle. The ground, from the project geotechnical report with borings in July 2025, is granular fill with some organics 1 to 6 feet thick, over stiff silt with fine sand lenses and traces of clay, over medium dense to dense stratified sand with some silt and gravel; bedrock was not encountered. Groundwater is 6 to 10 feet below grade, shown by two dashed lines on the neighbor's side, so it can stand above the bottom of the cut; on the excavation side a ghosted dashed line shows the dewatering by others holding water at least 2 feet below the bottom of the excavation. Drawn ghosted and dashed, because they are by others, are the excavation and the dewatered water level. Schematic only, not for construction; the section's pile and hole widths and the soil boundaries are not to scale; pending professional-engineer review.Fill, some organicsStiff siltStratified sand
Schematic — illustrative, not for construction; pending PE review.

Callouts

Select a numbered part below to read what it is and what it does.

Ready to scope your foundation?

Tell us about the project and we'll put together a detailed quote within 3 days. We generally work with general contractors.

Or email plans to bids@earthsupportcorp.com

CallEmailStart Quote