Earth Support Corp
Completed· October 2026

Drilled Shafts · Acton, MA

Rock-Socketed Piers for a Solar Carport, Acton

Eleven 36 in drilled concrete piers for a solar carport, on a site where the borings showed hard bedrock from about 7.5 ft down, boulders, and groundwater between about 6 and 13 ft.

12345678
Schematic — illustrative, not for construction; pending PE review.

The problem

Eleven 36 in drilled concrete piers for a solar carport, on a site where the borings showed hard bedrock from about 7.5 ft down, boulders, and groundwater between about 6 and 13 ft.

The engineered approach

Temporary steel casing held the overburden where it was wet or loose, then each shaft was cut into the rock to its design embedment of 9 to 12.5 ft. Each pier then got its reinforcing cage and an anchor-rod group set to a template before 5,000 psi concrete went in.

Outcomes for the GC

  • 11 piers drilled and poured, 9 of them socketed into rock
  • Rock came in as shallow as 3 ft, shallower than the borings showed
  • Every shaft logged by an independent geotechnical inspector

How we built it

A schematic section of the drilled shafts system for this Acton, MA job. Scroll to build it in construction order, or select a callout to read the detail.

Schematic cross-section of two of the eleven 36 inch rock-socketed piers for a solar carport in Acton, Massachusetts, drawn at the 9 and 12.5 foot ends of the design embedment: one with rock at about 3 feet, shown finished under a canopy column by others, and one cased through wet overburden to rock at about 7.5 feet, shown during the pour.An illustrative section along a row of the eleven 36 inch drilled, cast-in-place concrete piers Earth Support built for a solar carport in Acton, Massachusetts, completed in October 2026. The ground is a short run of fill, then glacial till with boulders, over hard bedrock. The project borings put the top of the rock at about 7.5 to 18 feet, with groundwater at about 6 to 13 feet; the independent drilled-shaft logs then found rock in 9 of the 11 shafts, as shallow as about 3 feet, so the bedrock surface is drawn rising from about 7.5 feet on the right to about 3 feet on the left. Two piers are drawn, at the two ends of the 9 to 12.5 foot design embedment, and the pairing of rock depth with embedment is illustrative. The left pier, shown finished, meets rock at about 3 feet and is drilled 9 feet, so most of it is rock socket. The right pier, shown during the pour, meets rock at about 7.5 feet under wet overburden and is drilled 12.5 feet. In construction order: temporary steel casing is set through the overburden (casing was used at 6 of the 11 piers, where the overburden was wet or loose), the overburden is drilled out, the rock socket is cut to design embedment, a reinforcing cage is set, the anchor-rod group is set to a template held on a frame over the hole, the pier is poured with 5,000 psi concrete up into a formed stick-up above grade, and the casing is pulled as the concrete goes in. Drawn dashed and ghosted, because it is by others rather than Earth Support, is the solar canopy column and steel on the finished pier. The fill, till and rock bands, the boulders, the shape of the rock surface between the piers, the stick-up height and everything above grade are schematic, not to scale beyond the dimensioned figures, and not for construction, pending professional-engineer review.FillTill & bouldersHard bedrock
Schematic — illustrative, not for construction; pending PE review.

Callouts

Select a numbered part below to read what it is and what it does.

Ready to scope your foundation?

Tell us about the project and we'll put together a detailed quote within 3 days. We generally work with general contractors.

Or email plans to bids@earthsupportcorp.com

CallEmailStart Quote